Basic Maths and Reasoning MCQs (page 118 of 212)
Percentages, ratios, averages, profit and loss, speed and time, number series and simple logical reasoning, with the working shown for every answer.
4,221 questions. Select an option to check your answer, or open "Show answer". Showing 2341–2360.
- 2341.
24 workers can finish a job in 12 days. How many days will 36 workers take?
Show answer
Answer: B. 8 days
Total work = 24 × 12 = 288 worker-days. 288 ÷ 36 = 8 days.
- 2342.
16 workers can finish a job in 5 days. How many days will 2 workers take?
Show answer
Answer: C. 40 days
Total work = 16 × 5 = 80 worker-days. 80 ÷ 2 = 40 days.
- 2343.
4 workers can finish a job in 8 days. How many days will 2 workers take?
Show answer
Answer: C. 16 days
Total work = 4 × 8 = 32 worker-days. 32 ÷ 2 = 16 days.
- 2344.
8 workers can finish a job in 6 days. How many days will 3 workers take?
Show answer
Answer: C. 16 days
Total work = 8 × 6 = 48 worker-days. 48 ÷ 3 = 16 days.
- 2345.
10 workers can finish a job in 18 days. How many days will 6 workers take?
Show answer
Answer: C. 30 days
Total work = 10 × 18 = 180 worker-days. 180 ÷ 6 = 30 days.
- 2346.
16 workers can finish a job in 15 days. How many days will 10 workers take?
Show answer
Answer: C. 24 days
Total work = 16 × 15 = 240 worker-days. 240 ÷ 10 = 24 days.
- 2347.
16 workers can finish a job in 18 days. How many days will 4 workers take?
Show answer
Answer: C. 72 days
Total work = 16 × 18 = 288 worker-days. 288 ÷ 4 = 72 days.
- 2348.
20 workers can finish a job in 10 days. How many days will 8 workers take?
Show answer
Answer: C. 25 days
Total work = 20 × 10 = 200 worker-days. 200 ÷ 8 = 25 days.
- 2349.
4 workers can finish a job in 18 days. How many days will 8 workers take?
Show answer
Answer: C. 9 days
Total work = 4 × 18 = 72 worker-days. 72 ÷ 8 = 9 days.
- 2350.
6 workers can finish a job in 12 days. How many days will 12 workers take?
Show answer
Answer: B. 6 days
Total work = 6 × 12 = 72 worker-days. 72 ÷ 12 = 6 days.
- 2351.
15 workers can finish a job in 24 days. How many days will 45 workers take?
Show answer
Answer: C. 8 days
Total work = 15 × 24 = 360 worker-days. 360 ÷ 45 = 8 days.
- 2352.
4 workers can finish a job in 20 days. How many days will 10 workers take?
Show answer
Answer: B. 8 days
Total work = 4 × 20 = 80 worker-days. 80 ÷ 10 = 8 days.
- 2353.
24 workers can finish a job in 24 days. How many days will 8 workers take?
Show answer
Answer: B. 72 days
Total work = 24 × 24 = 576 worker-days. 576 ÷ 8 = 72 days.
- 2354.
4 workers can finish a job in 18 days. How many days will 6 workers take?
Show answer
Answer: B. 12 days
Total work = 4 × 18 = 72 worker-days. 72 ÷ 6 = 12 days.
- 2355.
16 workers can finish a job in 24 days. How many days will 8 workers take?
Show answer
Answer: B. 48 days
Total work = 16 × 24 = 384 worker-days. 384 ÷ 8 = 48 days.
- 2356.
16 workers can finish a job in 6 days. How many days will 12 workers take?
Show answer
Answer: C. 8 days
Total work = 16 × 6 = 96 worker-days. 96 ÷ 12 = 8 days.
- 2357.
4 workers can finish a job in 5 days. How many days will 10 workers take?
Show answer
Answer: B. 2 days
Total work = 4 × 5 = 20 worker-days. 20 ÷ 10 = 2 days.
- 2358.
8 workers can finish a job in 20 days. How many days will 2 workers take?
Show answer
Answer: D. 80 days
Total work = 8 × 20 = 160 worker-days. 160 ÷ 2 = 80 days.
- 2359.
18 workers can finish a job in 18 days. How many days will 2 workers take?
Show answer
Answer: B. 162 days
Total work = 18 × 18 = 324 worker-days. 324 ÷ 2 = 162 days.
- 2360.
4 workers can finish a job in 15 days. How many days will 15 workers take?
Show answer
Answer: C. 4 days
Total work = 4 × 15 = 60 worker-days. 60 ÷ 15 = 4 days.